HyProMag USA Secures Texas Hub Power Capacity as Permitting and Contractor Selection Advance

CoTec Holdings says HyProMag USA has secured electricity capacity with Oncor for its Texas rare earth magnet recycling and manufacturing project in Texas, while permitting and contractor selection continue.

Published:
Reading Time
3 min

CoTec Holdings Corp. (TSXV:CTH)(OTCQX:CTHCF) said its 50:50 joint venture, HyProMag USA LLC, has secured electrical power capacity with Oncor Electric Delivery Company LLC for its planned Texas Hub in Dallas-Fort Worth. The project remains under development, with permitting and contractor selection now progressing ahead of targeted commissioning and construction milestones.

#Power capacity secured for project stages

HyProMag USA has secured power capacity for the planned cutting and finishing operations and Phase 1 of the Texas Hub. The company also described a pathway to support Phase 2 through a sub-station upgrade. Electricity for the facility is expected to come predominantly from renewable energy resources.

The development update follows the start of formal power supply discussions announced on June 22, 2026. CoTec said the power arrangements relate to the Texas Hub’s planned rare earth magnet recycling and manufacturing activities.

#Permitting and contractor process underway

Weston Solutions, Inc. is advancing permitting work for the Texas Hub. Separately, Pegasus TSI, Inc. has begun a Request for Quotation process to identify a general contractor for the initial cutting and finishing operations.

Pegasus and BBA USA Inc. are HyProMag USA’s U.S.-based engineering, procurement and construction management firms.

#Initial operations targeted for H1 2027

HyProMag USA is targeting commissioning of the cutting and finishing facility in H1 2027. CoTec said the operation is expected initially to use neodymium iron boron, or NdFeB, magnet blocks supplied from HyProMag Group operations to make finished magnets.

The facility is designed to process NdFeB magnet blocks and support finished-magnet qualification under ASTM A977/A977M. Its quality systems are intended to align with ISO 9001 as well as customer-specific quality, performance and traceability requirements. HyProMag USA also describes the site as a training facility for NdFeB magnet finishing ahead of the wider Texas Hub development.

#Phase 1 and Phase 2 plans

CoTec said Phase 1 is targeted for completion in mid-2028. The company says this stage is designed to produce approximately 550 tpa of sintered NdFeB magnet blocks and finished magnets, alongside approximately 484 tpa of co-products, representing approximately 1,034 tpa of total payable production.

HyProMag USA’s Phase 2 plan envisions expansion to approximately 1,526 tpa of total payable production. Upon completion of Phase 2, the Texas Hub is expected to produce approximately 1,048 tpa of sintered NdFeB magnet blocks and cylinders, together with approximately 478 tpa of co-products, representing total payable production of approximately 1,526 tpa.

These timing and production statements are forward-looking. CoTec identified risks that could affect the plans, including financing availability, environmental and permitting risks, labour costs and shortages, material supply and price fluctuations, energy costs, equipment availability, contractor and subcontractor performance, project delays, cost overruns, extreme weather, and social, transport and geopolitical disruptions.

#HPMS technology and ownership

HyProMag USA is developing the Texas Hub around Hydrogen Processing of Magnet Scrap, or HPMS, technology. The company says the process supports magnet-to-magnet short-loop recycling and can accept feedstocks such as end-of-life electric vehicle motors, data-centre and industrial equipment, consumer electronics and manufacturing scrap without chemical processing.

HyProMag USA is owned equally by CoTec and HyProMag Limited. HyProMag Limited is wholly owned by Maginito Limited, whose ownership is listed as 79.4% by Mkango Magnetic Materials Limited and 20.6% by CoTec.

CoTec Chief Executive Officer Julian Treger said securing power, progressing permitting and starting contractor selection were milestones for the Texas Hub. He said the initial 2027 operations are expected to establish U.S. magnet finishing and qualification capabilities, while Phase 1 is expected to provide integrated recycling and magnet manufacturing capacity.

#Key Takeaways

  • HyProMag USA has secured power capacity with Oncor for the Texas Hub’s cutting and finishing operations and Phase 1.
  • Weston Solutions is advancing permits, while Pegasus TSI has started the process of selecting a general contractor.
  • Cutting and finishing commissioning is targeted for H1 2027, subject to the risks and uncertainties identified by CoTec.
  • Phase 1 completion is targeted for mid-2028, with approximately 1,034 tpa of total payable production designed.
  • Upon completion of Phase 2, the Texas Hub is expected to produce approximately 1,048 tpa of sintered NdFeB magnet blocks and cylinders and approximately 478 tpa of co-products, representing total payable production of approximately 1,526 tpa.