Silver Tiger Reports El Tigre Construction Progress, With December 2027 First Pour Target

Silver Tiger Metals has reported progress across engineering, procurement, earthworks and site facilities at its El Tigre Stockwork Project in Sonora, Mexico.

Published:
Reading Time
3 min

Silver Tiger Metals Inc. (TSX:SLVR)(OTCQX:SLVTF) has provided a construction update for its El Tigre Stockwork Project in Sonora, Mexico. The company says work remains on schedule for commissioning and first pour in December 2027, following the start of construction in the first quarter of 2026.

#Construction progress at El Tigre

Silver Tiger said a 285-person Mexican engineering and construction team is working at the site and has recorded 300,000 man-hours since construction began. The company has also appointed a mine construction executive team to work with Kappes, Cassiday & Associates (KCA) and Kappes, Cassiday del Norte S de RL de CV (KCN).

Detailed engineering under the engineering, procurement and construction management (EPCM) contract is 70% complete. Land clearing and flora/fauna management across the construction area have been completed, while improvements to the 46 km road connecting Colonia Morelos with El Tigre are 100% complete.

Installation of the permanent man camp is 72% complete, and the contractor camp is operating. Major earthworks contractors have been mobilised, with heap leach, ponds and process plant platforms 14% complete. Platforms for the crusher and ancillary buildings are 23% complete.

#Equipment procurement and civil works

Silver Tiger said procurement of long-lead equipment has been completed. The items listed by the company include the crusher plant, conveyor and stacking system, and the Merrill-Crowe plant and refinery.

Engineering work is also continuing with equipment vendors on the crushing plant and Merrill-Crowe processing plant. The company said contractors for civil works and structural steel erection will be selected after this engineering stage is completed.

#Capital spending and cash position

Silver Tiger reported that it has spent approximately US$24 million and committed US$72 million of the US$124 million projected capital expenditure for the El Tigre Stockwork Project. The release states that $100 million USD remains to be spent to complete construction.

The company also reported approximately US$120 million cash on hand. President and CEO Glenn Jessome said, according to the release, that all required money is available to complete construction.

#Project ownership and development structure

Silver Tiger describes El Tigre as a 100% owned silver and gold heap leach project covering over 37,000 hectares in Sonora, Mexico. The company’s Board of Directors has approved the construction decision. KCA and KCN are assisting with construction of the mine and process plant under the EPCM contract.

#Schedule and stated risks

Silver Tiger says commissioning and first pour remain targeted for December 2027. These statements are forward-looking information, and the company cautions that they depend on assumptions including the continuance of Silver Tiger and its subsidiaries as a going concern, general economic and market conditions, mineral prices, the accuracy of mineral resource estimates and the performance of El Tigre.

The company also identifies exploration and development risks, the possibility of failing to establish estimated mineral resources or mineral reserves, commodity-price volatility, variations in recovery rates and global economic conditions as factors that could cause actual results and future events to differ materially from those anticipated.

#Key Takeaways

  • Silver Tiger says El Tigre remains scheduled for commissioning and first pour in December 2027.
  • A 285-person construction team is on site and has logged 300,000 man-hours.
  • Detailed engineering is 70% complete, while permanent camp installation is 72% complete.
  • Long-lead procurement is complete for the crusher plant, conveyor and stacking system, and Merrill-Crowe plant and refinery.
  • The company reported approximately US$24 million spent, US$72 million committed from the US$124 million projected capital expenditure, and approximately US$120 million cash on hand.

Original source: Read original article