Fermi Says TensorWave Lease Has Not Yet Become Effective as Parties Work Toward Closing

Fermi says it and TensorWave continue working toward closing their Data Center Lease and Services Agreement, but specified conditions were not fully satisfied by October 31, 2026.

Published:
Reading Time
2 min

Fermi Inc. said its Data Center Lease and Services Agreement with TensorWave TEX1, LLC has not yet become effective after the October 31, 2026 closing date passed without an extension. The companies continue working through the remaining requirements, and neither party has exercised a right to terminate the agreement.

#Lease remains conditional

The agreement was signed in August 2026 by Fermi’s wholly owned subsidiary, Fermi Campus 1 LLC, and TensorWave. Its effectiveness depends on specified closing conditions being satisfied or waived.

Fermi said those conditions had not been fully met by October 31, 2026. The outstanding requirements include completing and delivering related work letters and guaranties, finalising operating schedules and a service-level agreement, obtaining Board approvals, and securing project-level financing sufficient to fund construction of the leased premises.

#Parties continue discussions

Fermi Chief Executive Officer Lee McIntire said Fermi and TensorWave remain committed to the Lease and are continuing to address the conditions required before closing. McIntire said Fermi expects to provide more information during its earnings call next week, or sooner if appropriate.

The company said neither Fermi nor TensorWave has exercised any right to terminate the Lease. The transaction therefore remains in progress and has not been completed.

#Financing and closing risks

Fermi identified project-level financing as one of the conditions required for the Lease to become effective. The company also said there is a risk that the closing conditions may not be satisfied or waived on the expected timetable or at all, and that project-level financing may not be obtained on acceptable terms. Fermi referred to additional risks in its filings with the U.S. Securities and Exchange Commission.

#Fermi America business context

Fermi, operating as Fermi America™, develops private electric grids that it describes as providing highly redundant power at gigawatt scale for intelligence and AI compute. The company says its leadership team has a combined 25 GW of experience and that it is developing a 17 GW next-generation private grid.

Fermi also says its behind-the-meter Project Matador campus is expected to combine a combined-cycle natural gas project, a clean new nuclear power complex, utility grid power, solar power and battery energy storage to support hyperscale AI and advanced computing.

#Key Takeaways

  • Fermi said its Lease with TensorWave has not yet become effective.
  • The October 31, 2026 closing date passed without an extension.
  • Outstanding conditions include documentation, operating arrangements, Board approvals and project-level financing.
  • Neither party has exercised a termination right, and discussions are continuing.
  • Fermi expects to provide more information during its earnings call next week, or sooner if appropriate.