Southern Energy Corp. reported stronger third-quarter sales and adjusted funds flow, while average production declined and an ongoing FERC transportation dispute remained unresolved.
Southern Energy Corp. (TSXV:SOU, AIM:SOUC) reported higher petroleum and natural gas sales for the third quarter of 2026 despite a decline in average production. The company also provided an update on its Terrible Creek 21-2 #2 well in Mississippi and said a transportation dispute before the Federal Energy Regulatory Commission remains unresolved.
Petroleum and natural gas sales reached $4.7 million in Q3 2026, an increase of 8% from the same period in 2025. Southern attributed the rise mainly to higher oil production and stronger realised oil and natural gas prices, partly offset by lower natural gas sales volumes.
Average production was 10,214 Mcfe/d, equivalent to 1,702 boe/d, with natural gas accounting for 91% of the total. This represented an 18% decline from Q3 2025, which the company attributed primarily to natural declines.
Average realised prices were $4.06/Mcf for natural gas and $87.91/bbl for oil, compared with $3.59/Mcf and $63.53/bbl, respectively, in Q3 2025. Southern reported an average natural gas premium of $1.11/Mcf, or approximately 37%, above the NYMEX Henry Hub benchmark during the quarter.
Adjusted Funds Flow from Operations was $1.1 million, up 7% from the same period in 2025. Net earnings were $0.5 million, or $0.00 per share on a basic and diluted basis. The earnings figure included a non-cash gain on warrant revaluation of $1.2 million.
Southern reported net debt of $17.4 million as at September 30, 2026, compared with $19.7 million as at September 30, 2025.
Following financing completed in February 2026, the company retired its senior secured Credit Facility, extended debt maturities to December 2028 and reduced the annual cash interest rate on its senior debt from 15% to 7%.
The Terrible Creek 21-2 #2 Cotton Valley well in the Williamsburg Field was the first of two commitment wells under a Joint Venture Wellbore Participation Agreement with a strategic partner. It was spud on August 11, 2026 and completed in October 2026.
During a 72-hour flow test conducted without fracture stimulation, the well flowed at a gross stabilised rate of 2.3 MMcf/d of natural gas plus 50 barrels of condensate per day. Southern described this as approximately 430 boe/d gross, or approximately 215 boe/d net to its 50% working interest.
The reported rates were measured on a restricted choke and are preliminary. Southern cautioned that the test results are not necessarily indicative of the rate the well will achieve once on production, after any future stimulation, over the long term or in terms of ultimate recovery. The company is also analysing downhole pressure data from the test and subsequent shut-in period to determine whether future fracture stimulation is warranted.
Southern said it was constructing the wellsite and production facilities needed to accommodate the new volumes and anticipated bringing the well on production within the next couple of weeks.
Southern said the Terrible Creek well results will inform the timing and design of the second Williamsburg commitment well, which is currently expected to be drilled in Q1 2027. The company is also evaluating the potential completion of the remaining City Bank drilled but uncompleted well at Gwinville in Q1 2027.
The timing and extent of planned capital expenditures will be informed by commodity prices, well performance and available liquidity.
Southern continues to work with FERC staff on a transportation dispute that resulted in approximately 400 boe/d of production being shut in from the Mechanicsburg and Greens Creek fields.
The formal settlement process ended without resolution during the third quarter, and the matter moved into the FERC evidentiary hearing process. The hearing process has commenced, with FERC trial staff issuing data requests to both parties. Southern said the timing and outcome remain uncertain.
Southern has a fixed-price natural gas hedge covering 5,000 MMBtu/d at $3.40/MMBtu through December 2026. The company said it will continue monitoring NYMEX pricing and basis differentials and may evaluate additional hedging as it considers its 2027 capital program.
Q3 2026 petroleum and natural gas sales rose to $4.7 million, up 8% from the same period in 2025.
Average production fell 18% to 10,214 Mcfe/d, or 1,702 boe/d, with 91% natural gas.
The Terrible Creek 21-2 #2 well recorded a preliminary 72-hour flow-test rate of 2.3 MMcf/d plus 50 barrels of condensate per day without fracture stimulation.
Southern reported net debt of $17.4 million and said debt maturities had been extended to December 2028.
The FERC transportation dispute remains unresolved, with the timing and outcome of the evidentiary hearing process uncertain.
Southern Energy Corp. announced its third quarter 2026 financial and operating results for the three and nine months ended September 30, 2026. The release covered financial performance, production, the Terrible Creek 21-2 #2 well and subsequent operational developments.
Southern Energy Corp. identifies its shares as trading on the TSXV under SOU and on AIM under SOUC.
Southern Energy Corp. reported petroleum and natural gas sales of $4.7 million during Q3 2026, up 8% from the same period in 2025. The company attributed the increase primarily to higher oil production and stronger realised oil and natural gas prices, partly offset by lower natural gas sales volumes.
Southern Energy Corp. reported average production of 10,214 Mcfe/d (1,702 boe/d), with 91% natural gas, during Q3 2026. Production decreased 18% from the same period in 2025, primarily due to natural declines.
Southern Energy Corp. reported average realised natural gas and oil prices of $4.06/Mcf and $87.91/bbl, respectively, during Q3 2026, compared with $3.59/Mcf and $63.53/bbl in Q3 2025. The company also reported an average natural gas price premium of $1.11/Mcf, approximately 37%, above the NYMEX Henry Hub benchmark.
Southern Energy Corp. generated $1.1 million of Adjusted Funds Flow from Operations in Q3 2026, up 7% from the same period in 2025. It reported net earnings of $0.5 million, or $0.00 per share on a basic and diluted basis, including a non-cash gain on warrant revaluation of $1.2 million.
Southern Energy Corp. reported net debt of $17.4 million as at September 30, 2026, compared with $19.7 million as at September 30, 2025. Following its February 2026 financing, the company retired its senior secured Credit Facility, extended debt maturities to December 2028 and reduced the annual cash interest rate on its senior debt from 15% to 7%.
Southern Energy Corp. said the Terrible Creek 21-2 #2 Cotton Valley well was drilled in the Williamsburg Field as the first of two commitment wells under a Joint Venture Wellbore Participation Agreement with a strategic partner. After completion in October 2026, the well produced a gross stabilised rate of 2.3 MMcf/d of natural gas plus 50 barrels of condensate per day during a 72-hour flow test without fracture stimulation, equivalent to approximately 430 boe/d gross and approximately 215 boe/d net to Southern's 50% working interest.
Southern Energy Corp. cautioned that the Terrible Creek 21-2 #2 flow-test rates were measured over a 72-hour test period on a restricted choke without fracture stimulation and are not necessarily indicative of the rates the well will achieve once on production, following any future stimulation, over the long term or in terms of ultimate recovery. The company also said its analysis of downhole pressure data from the flow test and shut-in period is preliminary.
Southern Energy Corp. said it was planning and constructing the necessary wellsite and production facilities and anticipated bringing the Terrible Creek 21-2 #2 well on production within the next couple of weeks. The company is analysing downhole pressure data to determine whether future fracture stimulation is warranted.
Southern Energy Corp. said it intends to use the Terrible Creek 21-2 #2 results to inform the timing and design of the second Williamsburg commitment well, which is currently expected to be drilled in Q1 2027. The company said its capital expenditure plans will be informed by commodity prices, well performance and available liquidity.
Southern Energy Corp. continues to work with Federal Energy Regulatory Commission staff on the transportation dispute that resulted in approximately 400 boe/d of production being shut in from the Mechanicsburg and Greens Creek Fields. The formal settlement process concluded without resolution during Q3 2026, the matter proceeded to the FERC evidentiary hearing process, and the timing and outcome remain uncertain.
Southern Energy Corp. is evaluating the potential completion of the remaining City Bank drilled but uncompleted well at Gwinville in Q1 2027. The company said the timing and extent of its planned capital expenditures will depend on commodity prices, well performance and available liquidity.
Southern Energy Corp. has a fixed-price natural gas hedge covering 5,000 MMBtu/d at $3.40/MMBtu through December 2026. The company said it intends to monitor NYMEX pricing and basis differentials and is prepared to consider hedging additional production volumes as market conditions evolve and as it evaluates its 2027 capital programme.