#Construction Progress Overview
Silver Tiger Metals Inc., based in Halifax, Nova Scotia, has provided a construction update on its El Tigre Project located in Sonora, Mexico. The company reports that the project’s construction is proceeding as planned, with a targeted commissioning date set for December 2027.
Currently, 166 personnel are on-site, and an impressive 100,000 man-hours have been logged since the commencement of construction. The team, which is primarily comprised of local engineering and construction specialists, is nearing completion of critical build-out activities.
#Key Milestones Achieved
Significant milestones in the project include the completion of the procurement process for long lead items, such as the crusher plant and the conveyor and stacking system. The detailed engineering work led by Kappes, Cassiday & Associates and Kappes, Cassiday del Norte S de RL de CV continues to progress on schedule as part of the Engineering Procurement and Construction Management Contract.
As part of environmental assessments, land clearing and flora/fauna management measures are reported to be 60% complete, indicating a responsible approach to development. Furthermore, road improvements along the 46 km route from Colonia Morelos to El Tigre are underway, with 25% of the upgrades already completed.
#Exploration Drilling Initiatives
In addition to construction, Silver Tiger has shifted focus to exploration drilling targeting high-potential vein systems located north of the main El Tigre site. This strategic direction aligns with findings outlined in the Preliminary Economic Assessment, which emphasizes the potential for significant exploration upside beyond current resource estimates.
The company's leadership expressed satisfaction with the progress, emphasizing that construction remains on track and the onboarding of additional personnel to approach 200 is anticipated.
#Conclusion
As the El Tigre Project advances, Silver Tiger Metals appears well-positioned to meet its timeline for commissioning and initial operational outputs. The combination of ongoing construction efforts and proactive exploration strategies suggests a robust trajectory for the project’s future.
#Key Takeaways
- Construction of Silver Tiger Metals’ El Tigre Project is on schedule, targeting commissioning for December 2027.
- 100,000 man-hours logged with 166 workers on-site, nearing a total workforce of 200.
- Procurement of critical machinery and equipment is complete, with earthworks currently in progress.
- Shifts to exploration drilling are underway, focusing on promising vein systems identified in recent assessments.
- Environmental management practices are actively being implemented, with land clearing reported at 60% completion.