Silver Tiger Metals Reports Progress on El Tigre Project Construction

Last Updated:
Reading Time
2 min

#Construction Progress Overview

Silver Tiger Metals Inc., based in Halifax, Nova Scotia, has provided a construction update on its El Tigre Project located in Sonora, Mexico. The company reports that the project’s construction is proceeding as planned, with a targeted commissioning date set for December 2027.

Currently, 166 personnel are on-site, and an impressive 100,000 man-hours have been logged since the commencement of construction. The team, which is primarily comprised of local engineering and construction specialists, is nearing completion of critical build-out activities.

#Key Milestones Achieved

Significant milestones in the project include the completion of the procurement process for long lead items, such as the crusher plant and the conveyor and stacking system. The detailed engineering work led by Kappes, Cassiday & Associates and Kappes, Cassiday del Norte S de RL de CV continues to progress on schedule as part of the Engineering Procurement and Construction Management Contract.

As part of environmental assessments, land clearing and flora/fauna management measures are reported to be 60% complete, indicating a responsible approach to development. Furthermore, road improvements along the 46 km route from Colonia Morelos to El Tigre are underway, with 25% of the upgrades already completed.

#Exploration Drilling Initiatives

In addition to construction, Silver Tiger has shifted focus to exploration drilling targeting high-potential vein systems located north of the main El Tigre site. This strategic direction aligns with findings outlined in the Preliminary Economic Assessment, which emphasizes the potential for significant exploration upside beyond current resource estimates.

The company's leadership expressed satisfaction with the progress, emphasizing that construction remains on track and the onboarding of additional personnel to approach 200 is anticipated.

#Conclusion

As the El Tigre Project advances, Silver Tiger Metals appears well-positioned to meet its timeline for commissioning and initial operational outputs. The combination of ongoing construction efforts and proactive exploration strategies suggests a robust trajectory for the project’s future.

#Key Takeaways

  • Construction of Silver Tiger Metals’ El Tigre Project is on schedule, targeting commissioning for December 2027.
  • 100,000 man-hours logged with 166 workers on-site, nearing a total workforce of 200.
  • Procurement of critical machinery and equipment is complete, with earthworks currently in progress.
  • Shifts to exploration drilling are underway, focusing on promising vein systems identified in recent assessments.
  • Environmental management practices are actively being implemented, with land clearing reported at 60% completion.

Original source: Read original article

Frequently Asked Questions

Silver Tiger Metals has reported that construction of the El Tigre Project is progressing well, with the build-out of the engineering and construction team nearing completion and significant milestones achieved, including the logging of 100,000 man-hours since the project's initiation.
The company has outlined December 2027 as the target date for commissioning and the first pour, which reflects a determined approach to meet project timelines.
Key achievements include the completion of procurement for long lead items, ongoing earthworks, and substantial progress in land clearing, indicating that the project is on track and well-managed.
The Engineering Procurement and Construction Management Agreement is being carried out in partnership with experienced firms, Kappes, Cassiday & Associates and Kappes, Cassiday del Norte S de RL de CV, ensuring professional oversight of the construction activities.
The company has transitioned to exploration drilling targeting high-potential vein systems, which aligns with their strategic growth plans and highlights the exploration upside identified in the recently filed Preliminary Economic Assessment.
The El Tigre Project spans over 37,000 hectares, and is positioned as a notable silver and gold heap leach project, fully owned by Silver Tiger Metals, suggesting a strong commitment and potential for significant output.
The company has reported that land clearing and flora/fauna management are 60% complete, demonstrating a proactive approach to environmental stewardship as part of the construction process.
With the significant construction progress and positive exploration results, investors can be cautiously optimistic about future production capabilities and the project's potential economic impact once operational.