Fermi Reports Third-Quarter Results and Conditional Hyperscaler Agreements for Project Matador
Fermi has entered agreements with an undisclosed investment-grade hyperscaler linked to 600 MW of planned capacity at Project Matador and reported a $141.6 million third-quarter net loss.
Fermi Inc. (NASDAQ:FRMI)(LSE:FRMI) reported its third quarter 2026 financial results and announced agreements with an undisclosed investment-grade hyperscale customer related to an initial 600 MW of power capacity at Project Matador. The arrangements include upfront funding and early development work, but the parties are still working toward a definitive long-term lease.
#Hyperscaler agreements remain subject to lease finalisation
The customer has committed to financial and development activities for the Project Matador development, which is scheduled to begin in 2027. Fermi said the arrangements were made before completion of a long-term lease as the parties continue negotiations.
One agreement provides for a $200 million prepayment connected with the proposed 600 MW development. A separate $15 million agreement covers early construction and site development activities intended to support the customer’s schedule.
Fermi and the customer are also finalising a $90 million structural steel and building materials purchase agreement. If completed, that arrangement would allow the customer to use long-lead materials that Fermi secured in advance for the planned construction of multiple data centre facilities at Project Matador.
The customer’s identity has not been disclosed. Fermi said the customer intends to use its infrastructure and advance development work to accelerate deployment at the site. The long-term lease and steel purchase agreement have not yet been finalised.
Fermi and TensorWave have ended the Data Center Lease and Services Agreement signed in August 2026. The AMD credit support agreement associated with TensorWave has also been terminated.
Fermi said it continues to work with the Texas Tech University System on Project Matador, including conditions under the land lease that must be addressed before vertical construction can begin. Texas Tech University System Chancellor Brandon Creighton said the university system remains committed to the project.
For the three months ended September 30, 2026, Fermi reported $315.5 million of total cash and restricted cash on hand. The company invested $133.4 million in Property, Plant, and Equipment during the quarter and $759.5 million during the nine months ended September 30, 2026. The net balance was approximately $1.67 billion.
Outstanding debt, net, was $958.4 million. Fermi said this reflected a $463.0 million net increase in borrowings under its convertible senior notes and equipment financing facilities.
The company recorded a $141.6 million net loss, equal to $0.22 per basic and diluted share. General and administrative expenses were $142.2 million, including $65.8 million of non-cash stock compensation and $21.5 million in financial advisory fees settled through the issuance of common stock.
Fermi said it remains pre-revenue and in the development phase, with spending directed toward buildout rather than operations.
Fermi America describes Project Matador as a behind-the-meter campus in the Texas Panhandle intended to combine natural gas, nuclear power, utility grid power, solar power and battery energy storage for AI and advanced computing.
Subject to entering into binding customer agreements, the project is expected to ramp to approximately 17 GW, with capital deployment matched to commercial commitments. Fermi said statements about generation capacity beyond currently permitted levels are subject to additional permits and approvals, financing, interconnection capacity, land acquisition and other factors, and that there can be no assurance that such capacity will be developed or achieved.
Fermi scheduled a conference call and webcast for 9 a.m. Eastern Time / 2 p.m. British Time on November 12, 2026, to discuss the results and project developments. The company said a replay would be available for a period of one year.
Fermi also plans to file its report on Form 10-Q for the quarter ended September 30, 2026, with the U.S. Securities and Exchange Commission.
Fermi entered agreements with an undisclosed investment-grade hyperscaler connected to an initial 600 MW development at Project Matador beginning in 2027.
The arrangements include a $200 million prepayment agreement and a $15 million early construction and site development agreement.
A $90 million structural steel and building materials purchase agreement remains under finalisation, as does the definitive long-term lease.
Fermi terminated its Data Center Lease and Services Agreement with TensorWave and the associated AMD credit support agreement.
For the three months ended September 30, 2026, Fermi reported a $141.6 million net loss, $315.5 million of cash and restricted cash, and $958.4 million of outstanding debt, net.
Fermi announced its third quarter 2026 financial results and multiple new agreements with an investment-grade hyperscaler to advance 600 megawatts (MW) of power capacity at Project Matador. The company also announced the termination of its Data Center Lease and Services Agreement with TensorWave and the associated AMD credit support agreement.
Fermi has entered into agreements with an undisclosed investment-grade hyperscale customer to advance an initial 600 MW of power capacity beginning in 2027. The agreements include a $200 million prepayment agreement and a $15 million early construction and site development agreement, while the parties are finalising a $90 million structural steel and building materials purchase agreement.
No, Fermi and the customer continue to work towards a definitive long-term lease. The customer is making financial and development commitments ahead of finalising a lease, and the customer’s identity remains confidential.
Fermi and the customer are finalising the $90 million structural steel and building materials purchase agreement. Fermi says the agreement would enable the customer to leverage critical long-lead materials secured in advance and accelerate the planned construction of multiple data centre facilities at Project Matador.
Fermi and TensorWave have terminated the Data Center Lease and Services Agreement signed in August 2026. The AMD credit support agreement associated with TensorWave was also terminated.
For the three months ended September 30, 2026, Fermi reported a $141.6 million net loss, or $0.22 per basic and diluted share. General and administrative expenses were $142.2 million, including $65.8 million of non-cash stock compensation and $21.5 million of financial advisory fees settled through the issuance of common stock.
Fermi reported $315.5 million of total cash and restricted cash on hand and $958.4 million of outstanding debt, net, as of September 30, 2026. The debt figure reflected a $463.0 million net increase in borrowings under the convertible senior notes and equipment financing facilities.
Fermi invested $133.4 million in property, plant and equipment during the three months ended September 30, 2026, and $759.5 million for the nine months ended September 30, 2026. The net balance was approximately $1.67 billion, and Fermi said capital deployment remains matched to commercial progress.
Fermi said it remains pre-revenue and in its development phase, with spending tracking buildout rather than operations. The company said the hyperscaler agreements are intended to help it move from pre-revenue, pre-lease activity to the next phase of growth, subject to the relevant customer arrangements.
Fermi America develops next-generation private electric grids intended to deliver highly redundant power at gigawatt scale for intelligence and AI compute. Project Matador is a behind-the-meter campus in the Texas Panhandle designed to integrate natural gas, nuclear, utility grid power, solar power and battery energy storage.
Fermi says Project Matador is expected to ramp to approximately 17 GW, subject to entering into binding customer agreements. The company states that generation capacity beyond currently permitted levels is subject to additional permits and approvals, financing, interconnection capacity, land acquisition and other factors, and that there can be no assurance that such capacity will be developed or achieved.
Fermi Inc. identifies its shares as trading on NASDAQ under NASDAQ:FRMI and on the LSE under LSE:FRMI. The company also describes Fermi America™ as listed on Nasdaq & LSE: FRMI.
Fermi made the announcement on November 12, 2026, covering the three months ended September 30, 2026. The company scheduled a conference call and webcast for 9 a.m. Eastern Time / 2 p.m. British Time on November 12, 2026, and said a replay would be available for a period of one year.
Fermi plans to file its report on Form 10-Q for the quarter ended September 30, 2026, with the U.S. Securities and Exchange Commission. The filing will also be made available through the SEC’s website and Fermi’s Investor Relations section.