Brazil Potash signs 28-year power agreement for Autazes Project
Published
FAQSIR Generated from this announcement View original release below for safe harbor and regulatory notices
Video summary
The video covers the same ground as the plain English summary below.
Announcement Summary
Brazil Potash Corp. (NYSE-American: GRO) announced a definitive agreement with Gera Center for a modular power plant serving the Autazes Project.
- The Build-Own-Operate agreement gives Gera Center responsibility to fund, build, own and operate the plant for 28 years: five years during construction and 23 years as backup power.
- The plant is expected to supply electricity for two mine shafts, the processing plant and the port/terminal until the grid connection line (SIN) is completed.
- The system comprises 45 modular containerized diesel generators, with initial capacity of 10 megawatts increasing to 20 megawatts over the first year.
- The agreement removes approximately $33 million of power-related spending from the Project's upfront construction budget and is expected to deliver approximately $10 million in net savings.
- During construction, the agreement establishes contractual availability levels of at least 98% each month and 98.5% each year.
- Initial mobilization is to be completed within 120 days following issuance of the Order to Proceed.
The company expects the system to operate in reserve mode as backup power after mining begins and the planned transmission line connects the site to SIN. Its offtake agreements cover approximately 91% of planned production, and Brazil's Profert program has been enacted to support domestic fertilizer production.